Construction of additional car parking at West Cumbria House, delivered alongside a live office refurbishment and sensitive site conditions near a watercourse.
West Cumbria House, Workington
Civil Engineering & Highways
Car Parks

New Car Park Construction for Council Offices at Lillyhall

Thomas Armstrong (Construction) Ltd was appointed by Cumbria County Council to construct additional car parking at West Cumbria House in Lillyhall, Workington. The 10-week project was delivered under NEC 3 Option A and completed on programme in August 2020.

The works were carefully planned to coordinate with an ongoing refurbishment of the office building, while managing public access, traffic constraints on Jubilee Road, and the site's proximity to an open watercourse. Our team utilised experience from the 2015 Flood Recovery Programme to mitigate risks associated with in-river working, and reinforced temporary fencing due to the exposed nature of the site.

Client

Cumbria County Council

Project Completed

August 2020

Duration

10 Weeks

Value

$420,000

Contract

NEC 3 Option A
No items found.
No items found.

Civil Engineering & Highways services delivered at West Cumbria House, Workington

Works Included

  • Earthworks
  • Drainage with attenuation
  • Lighting installation
  • Vehicle access barriers
  • Electric vehicle charge points
  • Permeable block paving
  • Bitumen macadam surfacing
  • Road markings

Project Achievements

  • Delivered within 10-week programme
  • No complaints from stakeholders or office users
  • Maintained clean highway access during groundworks
  • No environmental or Health & Safety incidents
  • Aligned with refurbishment programme without disruption