Center Parcs, Penrith

Design and construction of 34 new timber frame lodges, new arrivals lodge, and additional car parking as part of a large-scale development at Center Parcs, Penrith.
Center Parcs, Penrith
Building
Leisure, Hotels and Retail

Lodge Construction and Infrastructure Works at Center Parcs

Thomas Armstrong (Construction) Ltd delivered a large-scale development project at Center Parcs, Penrith, involving the construction of 34 new timber frame lodges and a new 10-bay arrivals lodge. The scheme also included the demolition of an existing arrivals building and the creation of 120 additional car parking spaces.

The new accommodation included 14 two-bedroom executive lodges, 7 three-bedroom executive lodges, 12 three-bedroom lodges with hot tubs, and one six-bedroom single-storey lodge. Throughout the 60-week programme, careful coordination was required to avoid disruption to the 5,000–6,000 guests on-site at any given time.

Client

Center Parcs, Penrith

Project Completed

April 2019

Duration

60 Weeks

Value

£7m

Contract

JCT Intermediate
No items found.
No items found.

Building services delivered at Center Parcs, Penrith

Works Included

  • Construction of 34 new timber frame executive lodges
  • Demolition of existing arrivals lodge
  • Construction of new 10-bay arrivals lodge
  • Creation of 120 new car parking spaces
  • External gas and water infrastructure
  • Gas boilers, radiator heating, and controls
  • Hot and cold water services
  • Ventilation, sanitaryware and drainage systems

Project Achievements

  • Delivered on programme
  • Zero reportable Health & Safety incidents
  • Zero environmental notices issued
  • 76% of subcontractors sourced locally
  • High client satisfaction and repeat tenders
  • Successfully managed logistics around live site with 5,000+ guests